INTERNATIONAL HOSPITAL CENTER OF TUNIS

1.LOT OF DEEP FOUNDATIONS & EXCAVATION ARMOURING FOR 2 BASEMENT CAR PARKS :

The work consisted of the construction of foundations on piles with a continuous hollow auger, with a diameter of 800 mm and a depth of 14 m. The support of the excavations for two underground car parks was carried out in a differentiated manner: on the side of the adjoining building, walls made of secant piles with a diameter of 800 mm and a depth of 14 m were put in place, while on the side of the streets, Lutetian walls made of CFA piles were installed, accompanied by concrete walls to ensure the stability of the excavations.

year

2011

client

SOCIETE I.H.C.T

location

Centre Urbain Nord de Tunis – Tunisie