COMBINED CYCLE POWER PLANT – 450 MW – RADES -C

1.Lot Prefabricated Driven Pile Foundations:

The foundation works were carried out using prefabricated driven piles, with a section of 45 x 45 mm, installed at a depth of 25 metres. These piles provide a robust and reliable base for the planned structures.

To validate the quality of the piles, loading tests were carried out, including a compression test up to failure and a lateral test up to failure. In addition, the piles were examined using mechanical impedance techniques and sonic tests, ensuring the conformity and solidity of the foundations.

year

2018

client

GAMA POWER SYSTEMS

location

RADES, TUNISIE