CONSTRUCTION OF AN OFFICE BUILDING BOUHAIRA 2

1.Lot Infrastructure :

Construction of deep foundation works using bored piles reaching a depth of 45 metres, support for the basement excavations using 12-metre-long sheet piles, and construction of the structure of two reinforced concrete basements. Inspection of the piles carried out using sonic tests.

1.Lot Superstructure :

Construction of the reinforced concrete structure and completion of the finishing works of a mixed-use building, comprising offices and shops, consisting of a ground floor and ten floors.

year

2019

client

SOCIETE IMMOBILIERE SIMOB

location

Lac 2, Tunis, TUNISIE